How many working days in year 2012?
Here is the detail of the calculation:
Because 2012 is a leap year, it has 366 days.
Let's remove 52 saturdays and 53 sundays. It remains 261 days.
Now, let's remove 8 public holidays that do not fall during a weekend and we obtain 253 working days in 2012.
Here is the list of these 8 public holidays:
1. New Year Holiday : Monday, 2 January, 2012
2. Women's Day : Thursday, 8 March, 2012
3. Radonitsa : Tuesday, 24 April, 2012
4. Labour Day : Tuesday, 1 May, 2012
5. Victory Day : Wednesday, 9 May, 2012
6. Independence Day : Tuesday, 3 July, 2012
7. October Revolution Day : Wednesday, 7 November, 2012
8. Christmas Day : Tuesday, 25 December, 2012
And here are the 2 public holidays falling on a weekend:
1. New Year Holiday : Sunday, 1 January, 2012
2. Orthodox Christmas : Saturday, 7 January, 2012